The Emmanuel Journey

The Church Journey

Establishing the LEP

The whole concept of an Anglican/Methodist Covenant was alive in the minds of Methodist Church from the late

 

1970’s but sadly this failed to come to fruition. The concept was reborn in the late 1990’s when the Minister of the 

 

Methodist Church and the Vicar from the Anglican Church discussed a possible way forward for the two Churches

 

to share one building in an area ripe for mission. Many shared Worship and social events took place over the next

 

few years and folk began to know and value each other. 

 

 

The  Council offer to buy the Methodist Church (Salford Methodist Community Church) under a compulsory

 

purchase order was agreed and joint planning meetings began in earnest. In 2006 the Anglican Church

 

(St Ambrose) moved into the Methodist Church following a fire in their building and for a while worshiped in

 

a small room separate from the Methodist congregation. A series of away days ironed out the minor

 

difficulties and devised a way forward as it had now become apparent that both parties wanted to not only

 

share mission within the community but importantly wanted to become one in worship. Thus the two churches

 

came together as a Local Ecumenical Partnership and so the Emmanuel Church and Centre was born from the

 

vision of unity to Worship and serve the Community together. 

 

 

Building the Emmanuel Church, Centre & Appartments

Ministers and members of the Church laying the Foundation to the Building.


A Contract was entered into with a builder in May 2007. Later, a Legal agreement was drawn up in order to part

 

company with that builder and a new contract with an alternative builder was agreed in March 2008. Building work

 

now came to a halt and the Construction company was instructed and secured the site in March 2008 whilst

 

discussions took place with them to endeavour to negotiate a completion cost. The church was approached by a

 

new builder in October 2008. Unfortunately this builder went into administration in May 2009. A local business had

 

been subcontracted to complete the works in July 2009 but again, the builder went into administration in September

 

2010

 

 

The Building of the Emmanuel Centre Community Hall.

 

A new builder then reached agreement to complete the works on an ad-hoc basis from September 2010 until

 

(approximately) May 2012 . From then on building work was at a standstill untill 2014.  In the early summer of 2011

 

the community centre was signed off by building control which meant that the Church could then move into the

 

Community Centre. The twenty-two appartments on the three floors above had previously been completed and

 

were occupied.

 

The twenty-two affordable appartments above the Emmanuel Centre.

 

In February 2013 the City Council awarded the church a Regeneration Grant of £60,000, in order to complete the

 

outside works including the car park. This work was completed in February 2014. During the course of completing

 

the outside works upper brick work problems were discovered and all safety issues were addressed. There had

 

been an additional storm damage which has resulted in loss of ridge tiles on the Sports Hall roof and internal

 

damage to the ceiling/insulation tiles. This latter was an insurance claim and repairs begin Thursday 27th February

 

2014. The Church  worshiped in the Community Room each Sunday. The remainder of the week a wide range of

 

community groups occupy the Centre which is staffed by volunteers. 

 

 

The Worship space was completed and was officially opened and dedicated on 4th July 2015. Throughout the entire

 

journey the churches benefited from the support of the Anglican Team and the Methodist Circuit and indeed the

 

District and Connexion.